- Substrate Cleaning and Dry Surface Preparation — Inspect the wall substrate for stability, removing loose particles, dust, oil, or existing moisture. Ensure the facade surface is dry and level within acceptable construction tolerances before layout marking.
- Precision Layout and 45-Degree Miter Cutting — Measure installation lines precisely. Cut the rigid polyurethane profiles at 45-degree miter angles for corners and corner joints using a fine-toothed mechanical saw to ensure tight fitting connections.
- Continuous PU Adhesive Application — Apply a continuous, uninterrupted line of polyurethane (PU) mounting adhesive along the back bonding tracks of the profile. Do not use silicone adhesive under any circumstances.
- Mechanical Anchor and Cross Screwing — Press the profile firmly against the wall and install mechanical stainless steel screws through the profile into the wall structure. Drive screws at opposing (cross) angles at all joint intersections to lock the miter seams.
- Putty Application and grana 180-220 Sanding — Fill all screw head indentations and joint seams with exterior polyurethane joint putty. After complete drying, sand the joint smooth using grana 180-220 sandpaper until the surface is seamless.
- System Priming and Double UV Topcoat Application — Apply an optional exterior system primer over sanded areas if desired. Finish the entire installation with at least two coats of elastic, UV-resistant exterior paint to protect against solar radiation and weathering.
Fase 1 : Preparazione del Fondo e Tagli d'Angolo (Tempo : 20 min)
Tracciate gli allineamenti laser e tagliate le aste da 2400-2440 mm a 45° calcolando lo sfrido 10% per variazioni a -100 °C / +80 °C.
Fase 2 : Applicazione Adesivo PUR a Cordolo Continuo (Tempo : 30 min)
Stendete cordoli continui di adesivo adesivo di montaggio a base PU (indurimento in circa un’ora) sul retro del profilo in densità 150-220 kg/m³ (obiettivo di produzione ~160 kg/m³) e avvitate le viti di sicurezza.
Fase 3 : Stuccatura Giunti e Finitura Protettiva UV (Tempo : 25 min)
Levigate le giunzioni con carta grana 180-220 (grana 180–220) e applicate 2 mani di pittura per esterni su primer primer acrilico bianco monocomponente. idrorepellente (inferiore all’1%). Offerte 7 giorni, consegna franco fabbrica.